Lead times, observed prices, and secondary-market listings from four dealer inventories (more being added) — weekly. Built for the people waiting 160 weeks for iron.
Read Issue #001 Search 358 live listings Order book (beta) Submit a quote
Tier-1 OEMs quote 2030–31 delivery on large power transformers while new, current-year units sit in the dealer channel, price-on-application. Buildouts are slipping on power equipment — industry estimates put 30–50% of planned 2026 US datacenter openings delayed or canceled with power equipment among the named bottlenecks. There is no price index, no availability data, no benchmark — a $20B+ market allocated by relationships and phone calls. Grid Desk is the data layer: what's available, what it costs, how long everything actually takes.